Rolling wave planning: work packages vs planning packages

Rolling wave planning details near-term work and holds less-defined far-term work in planning packages. As the future becomes clearer, planning packages are broken into detailed work packages, and this continues until all work is planned in detail.

Near-term detail, far-term packages

GAO's Schedule Assessment Guide says near-term effort is planned in more detail than long-term effort. Detailed activities are typically 4 to 8 weeks long and cover well-defined work, usually within 6 months to a year. Program management decides how long the detail period is.

Less-defined effort further out is held as planning packages, planned at a higher level. One package can stand for several months of work, a trade's work, or even a future contract or phase.

GAO's best practice is to plan the rolling wave to a design review, test or other major milestone rather than an arbitrary period such as 6 months. Too much detail too early can harm the schedule, because it needs constant revision.

Rules for planning packages

Each planning package must still trace to WBS elements and be logically linked in the schedule, so the critical path can be monitored. Packages on or near the critical path, or carrying significant risk, should be broken into smaller activities.

When the schedule is fully resource loaded, budgets for labor, travel, equipment and material are assigned to both work packages and planning packages, so the total cost to complete is known at the outset.

GAO's cost guide adds that work packages are detailed tasks, typically 4 to 6 weeks, defined by who authorizes the task and how the work will be measured and tracked.

How long a detailed activity should be

Near-term detail activities should generally be no longer than the program's reporting period. With monthly reporting that is about 22 working days or less. Long durations should be broken into shorter activities where logical breaks exist.

Durations should still be balanced. Very short ones, a day or less, may mean the schedule is too detailed. Activities should be decomposed only far enough to show hand-offs between activities.

Where the exam catches people

  • Believing far-term planning packages need no links or WBS traceability: they must trace to the WBS and be logically linked.
  • Believing more detail always means a better schedule: detailing ill-defined work too early forces constant revision.
  • Believing the rolling wave should follow a fixed calendar period: GAO prefers planning to a major milestone.
  • Believing planning packages carry no budget: budgets go to both work and planning packages.
  • Believing a five-month detail activity is fine under monthly reporting: it should be broken at its logical break points.

Written from PMI's documentation

Try 3 questions on this

Pick an answer to see why each option is right or wrong.

  1. On a program that reports monthly, a near-term detail activity is estimated to run five months. Its work has clear logical break points. Which technique is used to bring it in line with the reporting period?

    Right. In the game that’s Renown for your Predictive, Plan-Based Methodologies building.

    Not that one: A is right. In the game your Predictive, Plan-Based Methodologies building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    Decomposing the activity at its break points does that now, rather than waiting.

    Written from www.gao.gov/assets/d1689G.pdf

  2. To fully resource-load a program schedule, the scheduler assigns budgets for direct labor, travel, equipment and material so that the total cost to complete the program is identified at the outset. Which two of the following receive these budgets? (Choose two)

    Right. In the game that’s Renown for your Predictive, Plan-Based Methodologies building.

    Not that one: D,E is right. In the game your Predictive, Plan-Based Methodologies building would lose a little Renown, and this question would come back later.

  3. On an earned value program, a control account manager is breaking near-term effort into detailed units a few weeks long. Which two of the following define each of these work packages? (Choose two)

    Right. In the game that’s Renown for your Predictive, Plan-Based Methodologies building.

    Not that one: B,E is right. In the game your Predictive, Plan-Based Methodologies building would lose a little Renown, and this question would come back later.