Lags, leads and date constraints in a project schedule

A lag is a wait between two activities that uses no effort or resources, and a lead is a negative lag. A date constraint overrides network logic to fix when an activity may start or finish. GAO says all three should be used sparingly and justified, and the baseline schedule should not contain hard constraints.

Lags and leads

A lag delays a successor for a passage of time with no effort or resources, such as waiting for concrete to cure before stripping forms. A lead accelerates a successor so it overlaps its predecessor.

GAO warns that lags are static: they must be changed by hand and cannot be statused. They are often misused to force a start date or as risk buffers, and can distort float and the critical path. A lag that stands for a waiting period, such as document review, should be replaced with an activity that can be monitored, statused and mitigated.

GAO's example: a 2-day paperwork lag after an HVAC inspection uses up the inspection's 2 days of float, so the inspection shows as critical. Effort aimed at the inspection would be misdirected, because the lag causes the criticality.

Leads assume foresight about future events. GAO prefers to split the predecessor into smaller activities and use F–S links.

Types of date constraint

Soft constraints are start no earlier than (SNET) and finish no earlier than (FNET). They stop an activity moving earlier but let it slip later if predecessors are late.

Hard constraints are start no later than (SNLT), finish no later than (FNLT), must start on (MSON) and must finish on (MFON). The 'must' constraints set early and late dates equal, which removes all float and makes the activity critical at once.

When constraints are justified

An SNET constraint is valid when an activity cannot start before a fixed date and has no other logical dependency, for example when an outside party will not release a facility before a set date.

A customer-mandated date, including a contractual obligation, is not by itself a reason to constrain an activity. Ideally only the program start date is entered and every other date comes from logic and durations. Working schedules may use hard constraints to test float, but the baseline and official status updates should not contain them. Every lag and constraint should be justified in the schedule documentation.

Where the exam catches people

  • Believing a contract date should be entered as a must-finish-on constraint in the baseline: GAO says the baseline should not contain hard constraints.
  • Believing an SNET constraint stops an activity slipping: it only stops it starting early.
  • Believing a waiting period is best shown as a lag: GAO prefers an activity that can be monitored and statused.
  • Believing an activity shown as critical is always the real driver: a successor lag can make it look critical.
  • Believing a lead is a reliable way to overlap work: GAO prefers splitting activities and using F–S links.

Written from PMI's documentation

Try 3 questions on this

Pick an answer to see why each option is right or wrong.

  1. On a house build, a 2-day wait for paperwork after an HVAC inspection is modelled as a lag on the link to the next task. The inspection now shows as critical in the status report. Which technique is used to address the criticality?

    Right. In the game that’s Renown for your Predictive, Plan-Based Methodologies building.

    Not that one: C is right. In the game your Predictive, Plan-Based Methodologies building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    Efforts aimed at the inspection would be misdirected. A lag that stands for a waiting period should be replaced with an activity that can be monitored, statused and mitigated.

    Written from www.gao.gov/assets/d1689G.pdf

  2. A contract obliges delivery of a test article on 30 June. The program office is preparing the baseline schedule against which performance will be measured. Which technique is used to set the delivery milestone's date in that baseline?

    Right. In the game that’s Renown for your Predictive, Plan-Based Methodologies building.

    Not that one: A is right. In the game your Predictive, Plan-Based Methodologies building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    The milestone's date comes from the network: ideally only the program start is entered and every other date is calculated from logic and durations.

    Written from www.gao.gov/assets/d1689G.pdf

  3. Thermal testing must use a chamber that an outside agency will not release before 1 March. Testing has no other logical dependency, and it may slip later if its predecessors run late. Which tool can be used to model this?

    Right. In the game that’s Renown for your Predictive, Plan-Based Methodologies building.

    Not that one: A is right. In the game your Predictive, Plan-Based Methodologies building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    GAO's own case is a production line that will not be available until an outside entity finishes, where an SNET constraint legitimately stops work starting too early.

    Written from www.gao.gov/assets/d1689G.pdf