Lessons learned: identified vs learned, and making them stick

A lesson identified is an evidenced conclusion that names a problem, its root cause and a course of action. It becomes a lesson learned only after a planned implementation has been completed and evaluated as successful. UK guidance adds a fourth step, embedding, so the change is retained over time.

From observation to lesson

The UK Lessons Management Best Practice Guidance is built on the Observation, Insight, Lesson Identified, Lesson Learned (OILL) method. It has four processes: identification, prioritisation, implementation and embedding.

Identification has six steps: capture, analyse, identify, validate, report and share. Using two or more collection methods, such as feedback forms and group debriefs, improves the credibility of a lesson. Analysis looks at the what and the why of an issue, not just the who, and searches for trends, themes and insights.

Validation asks people involved in the event to check the draft lessons. Done with openness to challenge, it guards against groupthink and builds buy-in. The post-event report then lists the lessons identified and their recommendations.

Prioritising lessons

Lessons are recorded in a lessons management register, each with a unique code, a learning theme and the risk it relates to. Each lesson can be scored for how likely the issue is to recur and how severe the impact would be if it did. A prioritisation matrix combines the two scores into priority levels.

Owners are then assigned. The organization that identified a lesson may not be the one that implements the action.

Implementing and embedding

Implementation runs lead, plan, act, monitor, evaluate and report. Plans can be structured with why, what, who, when, where and how (5W1H). People need capability, opportunity and motivation for behaviour to change: knowledge and skills, a supportive environment, and an understanding of the goal.

The guidance describes change as unfreeze, move and refreeze. Communicating the reasons supports the unfreeze, leading by example supports the move, and chances to practise and rehearse the new way support the refreeze.

Embedding keeps the change in place after implementation ends. Without it, people can revert to old ways and the learning erodes.

Where the exam catches people

  • Believing a documented, validated lesson is a lesson learned: it is a lesson identified until implementation is completed and evaluated as successful.
  • Believing analysis should focus on who made the mistake: it focuses on the what and the why.
  • Believing implementation is the last step: embedding is needed so people do not revert to old ways.
  • Believing training alone changes behaviour: people also need opportunity and motivation.
  • Believing the team that identified a lesson must implement it: implementation owners may be different.

Written from PMI's documentation

Try 3 questions on this

Pick an answer to see why each option is right or wrong.

  1. After an emergency exercise, a team analyses observations and documents a problem, its root cause and a corrective course of action, and stakeholders validate it. No implementation has begun. Which artifact will be listed in the post-event report?

    Right. In the game that’s Renown for your Project Management Fundamentals and Core Concepts building.

    Not that one: B is right. In the game your Project Management Fundamentals and Core Concepts building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    Post-event reports list these lessons identified with their recommendations. It becomes a lesson learned only once a planned implementation has been completed and evaluated as successful.

    Written from www.gov.uk/government/publications/lessons-management-best-practice-guidance/lessons-management-best-practice-guidance-html

  2. After a lessons review, a public body is changing its procedures. Staff already understand why the change is needed, and leaders are modelling the new behaviour. The body now wants the new ways of working to become the settled norm. Which technique is used?

    Right. In the game that’s Renown for your Project Management Fundamentals and Core Concepts building.

    Not that one: A is right. In the game your Project Management Fundamentals and Core Concepts building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    Opportunities to practise and rehearse new ways of doing things support the refreeze, setting people up for success before wider-scale use.

    Written from www.gov.uk/government/publications/lessons-management-best-practice-guidance/lessons-management-best-practice-guidance-html

  3. The department wants to decide the order in which lessons from an exercise are acted on. It scores how likely each issue is to recur and how severe the effect would be if it did. Which tool can be used to combine the two scores?

    Right. In the game that’s Renown for your Project Management Fundamentals and Core Concepts building.

    Not that one: D is right. In the game your Project Management Fundamentals and Core Concepts building would lose a little Renown, and this question would come back later.