Contract types for the PMP: fixed price, cost plus and T&M

The pricing type decides who carries the risk. Fixed and firm prices move delivery risk to the supplier and need a fixed, clear scope; cost plus and time and materials leave most risk with the buyer, who keeps control over how the work is done.

Fixed and firm price

In the UK government's guidance, a fixed price agrees base prices at the outset and uplifts them by an agreed price index. A firm price is the same but with no indexation; at most an escalation factor agreed at tender, such as 2 percent a year. Other sources use these words differently, so read whether the price can move.

Both need a fixed scope and a clear specification. An ambiguous specification gives the supplier room to argue that some work is outside the price, so tighten the wording before tender. Firm pricing suits short contracts, generally up to three years. For longer contracts or uncertain inflation, the guidance calls fixed pricing with indexation commercial best practice.

Fixed pricing is not suitable where base prices cannot be estimated, such as an innovative design never costed before. There, cost plus may be the only option.

Cost plus and time and materials

Under cost plus the supplier is paid its directly incurred costs plus an agreed margin or fixed fee. Costs are tested as allowable or disallowable, so the arrangement is open book and the buyer audits what is claimed. It suits novel or first-generation contracts and pilots. It gives the buyer no price certainty and little supplier incentive to cut cost. As requirements become clear, parts of the contract can move to other pricing.

The Sourcing Playbook says that if the buyer wants to control how the services are delivered, it should use an input-based pricing model, normally cost plus or time and materials, and transfer little or no risk to the supplier. There should be no risk premium in the price.

Other approaches

Volume-based pricing pays a rate per unit used and suits a defined schedule of rates with variable demand. Payment by results ties payment to specified outcomes and transfers a lot of risk to suppliers, which can raise their prices. A guaranteed maximum price with target cost shares savings below the target, splits overruns above it equally, and caps what the buyer pays.

Where the exam catches people

  • Believing a fixed price works with a vague scope: fixed and firm pricing need a fixed, clearly specified scope.
  • Believing cost plus gives the buyer price certainty: the buyer carries the cost risk and cannot be sure of total spend.
  • Believing time and materials hands risk to the supplier: it is input-based, so the buyer keeps control and most of the risk.
  • Believing cost plus needs little oversight: it is open book, and the buyer must check that only allowable costs are paid.
  • Believing payment by results is low risk for suppliers: it transfers significant risk and can bring high risk premiums.

Written from PMI's documentation

Try 3 questions on this

Pick an answer to see why each option is right or wrong.

  1. A predictive project must contract a supplier for an innovative design that has never been built, so no one has a basis for pricing it. The sponsor wants price certainty. Which of the following contract types should the project manager select?

    Right. In the game that’s Renown for your Process building.

    Not that one: C is right. In the game your Process building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    Cost plus is suited to novel or first-generation contracts, and guaranteed cost recovery mitigates the supplier's risk when requirements are unclear.

    Written from www.gov.uk/government/publications/the-sourcing-and-consultancy-playbooks/risk-allocation-and-pricing-approaches-guidance-note-html

  2. On a predictive project, the organization will buy specialist engineering effort but wants its own engineers to direct exactly how the contractor's staff carry out the work. Which of the following pricing approaches should the project manager recommend?

    Right. In the game that’s Renown for your Process building.

    Not that one: B is right. In the game your Process building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    Time and materials is the input-based option here.

    Written from www.gov.uk/government/publications/the-sourcing-and-consultancy-playbooks/the-sourcing-playbook-html

  3. A predictive project has awarded a cost plus contract for a first-of-its-kind system. The finance office worries the supplier will charge expenses the contract does not allow. Which of the following should the project manager do?

    Right. In the game that’s Renown for your Process building.

    Not that one: D is right. In the game your Process building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    The guidance says cost plus requires transparency over the supplier's actual costs, which is why these arrangements are open book, and that the buyer must manage them so only allowable costs are recovered.

    Written from www.gov.uk/government/publications/the-sourcing-and-consultancy-playbooks/risk-allocation-and-pricing-approaches-guidance-note-html