Conflict of interest under the PMI Code of Ethics

Under the PMI Code of Ethics you disclose any real or potential conflict of interest to the appropriate stakeholders, then stay out of the decision until there is an approved mitigation plan and their consent to proceed. You treat even the appearance of a conflict as a conflict, however impartial you believe you are.

What counts as a conflict

The Code's glossary defines a conflict of interest as a decision or action that would benefit you or someone you owe loyalty to while harming another party you owe a similar duty of loyalty. The Code says research with practitioners found conflicts of interest are among the situations they face most often, and that a common problem is not recognizing one.

Example: you sit on a panel scoring supplier bids and one bidder is owned by your sibling. You owe loyalty to your employer and you have a family tie to a bidder. That is a conflict, even if you are sure you would score fairly.

The three conditions before you take part

The mandatory Fairness standard says that once you realize you have a real or potential conflict, you refrain from the decision and from trying to influence it unless or until three things are in place: full disclosure to the appropriate stakeholders, an approved mitigation plan, and the stakeholders' consent to proceed.

Disclosure alone is not enough. If you told the sponsor your spouse works for a vendor under evaluation and the sponsor only acknowledged it, you stay out of the evaluation until a mitigation plan is approved and consent is given. The glossary adds that the only way to resolve conflicting duties is to disclose and let those affected decide how you proceed.

Fairness in bidding and hiring

The Code asks you to give equal access to information to those authorized to have it, and its comment applies this to bidding. If one prospective supplier phones with a question that exposes an ambiguity in the requirements, the clarification goes to every bidder, not just the caller.

The same chapter forbids hiring, firing, rewarding or awarding contracts on favoritism, nepotism or bribery, and asks you to give equal consideration to all qualified candidates.

Where the exam catches people

  • Believing confidence in your own impartiality settles it: the Code says to treat the appearance of a conflict as a conflict.
  • Believing disclosure lets you carry on: you also need an approved mitigation plan and the stakeholders' consent.
  • Believing you should decide the fix yourself, such as excluding the relative's firm: those affected decide how you proceed after you disclose.
  • Believing you can answer one bidder's question privately: bidders must have equal access to information.

Written from PMI's documentation

Try 3 questions on this

Pick an answer to see why each option is right or wrong.

  1. The project manager sits on a panel scoring supplier bids. One bidder is owned by the project manager's sibling, but the project manager is confident of scoring every bid impartially. Which of the following should the project manager do?

    Right. In the game that’s Renown for your People building.

    Not that one: D is right. In the game your People building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    The required response is to disclose it to the appropriate stakeholders, who then decide how the practitioner should proceed.

    Written from www.pmi.org/-/media/pmi/documents/public/pdf/ethics/pmi-code-of-ethics.pdf

  2. The project manager has told the sponsor that a spouse works for one of the vendors under evaluation. The sponsor acknowledged it but has given no further direction. Which of the following should the project manager do?

    Right. In the game that’s Renown for your People building.

    Not that one: D is right. In the game your People building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    Here only the disclosure has happened.

    Written from www.pmi.org/-/media/pmi/documents/public/pdf/ethics/pmi-code-of-ethics.pdf

  3. During a competitive bid, one prospective supplier phones the project manager with a question that reveals an ambiguity in the requirements. Which of the following should the project manager do?

    Right. In the game that’s Renown for your People building.

    Not that one: A is right. In the game your People building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    The clarification therefore goes to every bidder, not only the one who asked.

    Written from www.pmi.org/-/media/pmi/documents/public/pdf/ethics/pmi-code-of-ethics.pdf