The Green Book splits the cost of risk into impact costs, correction costs and prevention costs. Spending to prevent, reduce, transfer or avoid a risk is a prevention cost and goes into the proposal's core costs, while risk transfer aims to give each risk to the party best able to manage it.

Three kinds of cost

Impact costs occur when a risk materializes, such as lost service during a system outage. Correction costs are the cost of recovering, such as bringing the system back online. Prevention costs pay for measures to prevent, reduce, transfer or avoid a risk, such as investing to make the system more resilient.

A mitigation usually costs money now and saves impact and correction costs later. The Green Book says to weigh those costs and benefits to judge whether, and how far, the mitigation is value for money. Lowering a risk is not enough on its own.

Where each cost goes

Prevention costs go in the core costs of the proposal. Contingency is separate: it covers residual risk, meaning the optimism bias adjustment that remains plus the value of risks not prevented. Paying a second supplier to stand ready in case the main one fails is a prevention cost, so it belongs in core costs.

Contingent liabilities are potential future costs that arise only if certain events occur. The Green Book's example is the cancellation charge if a contract is ended early. They are appraised and included in the expected cost of risk.

Transferring risk

Transferring risk to a contractor usually has a price, so weigh its benefits against that cost. The Green Book says the purpose is not to transfer every risk, but to allocate each specific risk to the organization best able to manage it.

Where the exam catches people

  • Believing any measure that lowers risk should be funded: the Green Book weighs its prevention cost against the impact and correction costs it saves.
  • Believing prevention spending belongs in contingency: it goes in the core costs; contingency covers residual risk.
  • Believing the best contract pushes all risk onto the contractor: risks go to the party best able to manage them.
  • Believing early-termination fees are ignored until they happen: they are contingent liabilities, included in the expected cost of risk.

Written from PMI's documentation

Try 3 questions on this

Pick an answer to see why each option is right or wrong.

  1. While appraising a predictive project, the sponsor agrees to pay a second supplier to stand ready in case the main supplier fails. The project manager is placing this payment in the financial case. Which of the following should hold it?

    Right. In the game that’s Renown for your Business Environment building.

    Not that one: B is right. In the game your Business Environment building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    Contingency is a separate allowance covering residual risk: the remaining optimism bias adjustment and the value of risk not prevented.

    Written from www.gov.uk/government/publications/the-green-book--2/the-green-book-2026

  2. While appraising a proposal, the project manager includes the fees the organization would owe if it ended a supplier contract early. Which of the following is the project manager accounting for?

    Right. In the game that’s Renown for your Business Environment building.

    Not that one: A is right. In the game your Business Environment building would lose a little Renown, and this question would come back later.

  3. While drafting a contract for a predictive construction project, the sponsor wants the contractor to carry as much of the project's risk as possible. Which of the following should the project manager recommend?

    Right. In the game that’s Renown for your Business Environment building.

    Not that one: A is right. In the game your Business Environment building would lose a little Renown, and this question would come back later.