Agile estimation: story points, planning poker and velocity

Agile teams usually estimate in units other than hours, most often story points, by comparing items with each other. Velocity is the total of the estimates for the stories finished in an iteration, and the team uses it to plan how much to take on next.

Story points and relative estimation

The Agile Alliance glossary says agile teams generally prefer to estimate in units other than man-days or man-hours, and that story points are probably the most widespread unit. In relative estimation, the team compares items or groups them by similar difficulty instead of estimating each one in absolute units of time. Tee-shirt sizes are a non-numeric variant.

The glossary gives the main benefit as avoiding false precision and avoiding confusing estimates with commitments. It also warns that estimates carry uncertainty, are not commitments, and may be updated up or down when new information arrives.

Planning poker

In planning poker each member holds numbered cards. The Product Owner explains a story, everyone picks a card in private, and all cards are shown at once. The people with the highest and lowest estimates explain their reasoning, and the team may vote again.

The format keeps sessions moving, draws on quieter members, and brings risks into the open. The glossary warns against forcing a consensus number, because wide early spread shows how uncertain the team is.

Velocity

Velocity is the sum of the estimates of the stories completed in an iteration. Partly done stories count for nothing: two finished 2-point stories plus a 3-point story that is 80% done give a velocity of 4. If velocity stays roughly steady, the team can forecast how many iterations the remaining work needs.

The glossary calls velocity a measurement made after the fact. Individual velocity is meaningless, and comparing velocity between teams is not meaningful because teams estimate differently.

Who sizes the work in Scrum

The Scrum Guide says the Developers who will do the work are responsible for sizing Product Backlog items. The Product Owner may influence them by helping them understand trade-offs but does not set the size.

At Sprint Planning, the Developers' forecast is more confident the more they know about their own past performance, their upcoming capacity and their Definition of Done. A team that has run three Sprints should use its own record, not an industry benchmark or another team's velocity.

Where the exam catches people

  • Believing the Product Owner or a manager can set an item's size: the Developers doing the work size it.
  • Believing velocity can be compared across teams or per person: it belongs to one team and is not comparable.
  • Believing a partly finished story adds to velocity: only completed stories count.
  • Believing an estimate is a commitment: estimates carry uncertainty and should be updated as more is learned.
  • Believing planning poker must end in agreement: forcing consensus hides how uncertain the team is.

Written from PMI's documentation

Try 3 questions on this

Pick an answer to see why each option is right or wrong.

  1. During Product Backlog refinement on an adaptive project, the Product Owner thinks the team's size for a high-value item is too large and wants a smaller size recorded. Which of the following should the project manager support?

    Right. In the game that’s Renown for your Process building.

    Not that one: A is right. In the game your Process building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    The Product Owner may influence them by helping them understand and select trade-offs, but does not set the size, even though the Product Owner is accountable for the Product Backlog.

    Written from scrumguides.org/scrum-guide.html

  2. At Sprint Planning for a new product's fourth Sprint, a manager suggests the Developers size the selection using an industry benchmark of output per developer. Which of the following should the Developers base it on?

    Right. In the game that’s Renown for your Process building.

    Not that one: C is right. In the game your Process building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    After three Sprints, this team has its own record to use. An industry figure describes other teams' work, not this team's.

    Written from scrumguides.org/scrum-guide.html

  3. At the end of each iteration, an agile team adds up the estimates of the user stories it completed, so it can compare one iteration with the next. Which of the following does this total represent?