MoSCoW prioritization and WSJF explained for the CAPM

MoSCoW sorts backlog and roadmap items into must haves, should haves, could haves and will not haves, and GOV.UK recommends it for building consensus in a team. Other methods suit other needs: a prioritisation quadrant balances different types of work, and SAFe's Weighted Shortest Job First ranks work by cost of delay divided by duration.

The four MoSCoW categories

Must haves are essential things the product cannot function without.

Should haves can greatly improve the product but are not crucial to making it function.

Could haves can improve the service but will not have too negative an impact if left out at this stage.

Will not haves are low priority things the team has agreed not to do.

How GOV.UK says to prioritise

Prioritise regularly, for example weekly for the sprint backlog and quarterly for the service roadmap. Base decisions on performance analysis, user research and stakeholder input. The person leading the exercise uses a clear method and involves the delivery team and stakeholders.

A backlog holds more than new features: support tickets and technical debt tasks need priority too. Something like a prioritisation quadrant helps make sure enough different types of work are prioritised. Priorities also shift by phase: in beta you prioritise improvements as you test, and in live you balance support work with improvements.

Weighted Shortest Job First in SAFe

SAFe defines WSJF as a prioritization model used to sequence work for maximum economic benefit. It is estimated as the relative cost of delay divided by the relative job duration, using relative user and business value, time criticality, risk reduction or opportunity enablement, and job size.

Where the exam catches people

  • Believing 'should have' means essential: should haves greatly improve the product but are not crucial to making it function.
  • Believing 'will not have' items were rejected by the product owner alone: they are things the team has agreed not to do.
  • Believing MoSCoW is the right tool to balance features, support tickets and technical debt: GOV.UK points to a prioritisation quadrant for that.
  • Believing WSJF ranks by value alone: it divides cost of delay by job duration.

Written from PMI's documentation

Try 3 questions on this

Pick an answer to see why each option is right or wrong.

  1. To build consensus, a team sorts the items in its backlog and roadmap into must haves, should haves, could haves and items it has agreed not to do. Which technique is used?

    Right. In the game that’s Renown for your Business Analysis Frameworks building.

    Not that one: D is right. In the game your Business Analysis Frameworks building would lose a little Renown, and this question would come back later.

  2. The product backlog of a live government service holds user stories for new features, support tickets and tasks to address technical debt. The team wants each type of work to get enough attention when it orders the backlog. Which tool can be used?

    Right. In the game that’s Renown for your Business Analysis Frameworks building.

    Not that one: B is right. In the game your Business Analysis Frameworks building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    It suggests something like a prioritisation quadrant to make sure enough different types of work are prioritised.

    Written from www.gov.uk/service-manual/agile-delivery/deciding-on-priorities

  3. A SAFe Agile Release Train orders its backlog for maximum economic benefit by dividing each item's relative cost of delay by its relative duration. Which technique is used?

    Right. In the game that’s Renown for your Business Analysis Frameworks building.

    Not that one: B is right. In the game your Business Analysis Frameworks building would lose a little Renown, and this question would come back later.