Accept, avoid, mitigate or transfer risk: Security+ explained

Accept a risk when it is within the organization's risk tolerance. Avoid it when it exceeds tolerance and no practical safeguard exists, by dropping the activity or technology that causes it. Mitigate it by adding safeguards that lower it, and transfer it by shifting liability to another party, such as an insurer.

The four responses

NIST SP 800-39 lists the ways to respond to risk as acceptance, avoidance, mitigation, sharing and transfer, or a combination of them. NIST defines risk response as accepting, avoiding, mitigating, sharing or transferring risk.

Acceptance is the right response when the risk is within the organization's risk tolerance. SP 800-39's example is a data center in a region where major earthquakes are rare: the organization accepts that an earthquake is possible but judges it not cost-effective to address.

Avoidance may be right when the risk exceeds tolerance. It means removing or changing the activity or technology behind the risk. SP 800-39's example: an organization finds a planned network connection between two domains carries unacceptable risk, safeguards are not practical, so it removes the connection and moves data manually by storage device, an air gap.

Mitigation, also called risk reduction, handles the part of the risk that cannot be accepted, avoided, shared or transferred. It can use common controls, process re-engineering, or new or enhanced management, operational or technical safeguards.

Transfer and sharing

Risk transfer shifts the entire responsibility or liability to another organization, for example through insurance. Risk sharing shifts only part of it, usually to an organization better placed to address it.

SP 800-39 states that risk transfer reduces neither the likelihood of harmful events nor the harm they cause. Insurance pays for losses. It does not stop the outage. If the goal is to reduce the harm while the system stays in service, the answer is mitigation.

Choosing between them

Read the scenario for three clues. Is the risk within tolerance? Then accept. Is it beyond tolerance with no practical safeguard, and can the activity be dropped? Then avoid. Must the activity continue with less risk? Then mitigate. Is the aim to move the financial liability elsewhere? Then transfer.

An insurance offer does not make transfer the right answer. If the risk is already within tolerance, acceptance is the appropriate response even when coverage is available.

Where the exam catches people

  • Believing buying insurance reduces the risk itself: transfer moves liability but reduces neither likelihood nor harm.
  • Believing an available insurance policy means you should transfer: a risk within tolerance is accepted.
  • Believing avoidance means ignoring a risk: avoidance removes or changes the activity or technology that causes it.
  • Believing avoidance fits when the system must stay in service: if the activity must continue, the response is mitigation.
  • Believing mitigation means only technical controls: it can also be common controls, process re-engineering, or management and operational safeguards.

Written from CompTIA's documentation

Try 3 questions on this

Pick an answer to see why each option is right or wrong.

  1. A company's only data center is in a region where damaging earthquakes are rare. Its assessment finds the earthquake risk is within the company's risk tolerance, and an insurer offers earthquake coverage. Which of the following risk treatments is the most appropriate?

    Right. In the game that’s Renown for your Security Program Management and Oversight building.

    Not that one: C is right. In the game your Security Program Management and Oversight building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    Its own example is a data center in a region where major earthquakes are infrequent: the organization accepts that earthquakes are possible but judges it not cost-effective to address the risk.

    Written from nvlpubs.nist.gov/nistpubs/Legacy/SP/nistspecialpublication800-39.pdf

  2. A utility planned a network link between its plant control systems and its corporate network, but found the risk unacceptable and no practical safeguard. It drops the link and moves files by removable media instead. Which of the following risk treatments is this?

    Right. In the game that’s Renown for your Security Program Management and Oversight building.

    Not that one: A is right. In the game your Security Program Management and Oversight building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    Its example is this one: an organization finds a planned network connection between two domains carries unacceptable risk, safeguards are impractical, so it eliminates the connection and uses an air gap with manual transfers.

    Written from nvlpubs.nist.gov/nistpubs/Legacy/SP/nistspecialpublication800-39.pdf

  3. A company's board directs that the harm a ransomware outage would cause to its billing operations be reduced. The billing system must remain in service. Which of the following risk treatments meets this direction?

    Right. In the game that’s Renown for your Security Program Management and Oversight building.

    Not that one: C is right. In the game your Security Program Management and Oversight building would lose a little Renown, and this question would come back later.

    Show the full explanation and doc quotes

    NIST SP 800-39 states that risk transfer reduces neither the likelihood of harmful events nor their consequences in terms of harm to organizational operations, so it cannot meet a direction to reduce the harm.

    Written from nvlpubs.nist.gov/nistpubs/Legacy/SP/nistspecialpublication800-39.pdf